Master Layout Plan
×
Approvals
Planning Permit No:
PPA/WDCN13/07259/2024
Date of Permit:
2024-08-17
Building Permission No:
BA/WDCN13/05820/2024
Date of Permit:
2024-08-17
Project Update Images
-
-
-
-
- 3rd floor roof concrete is completed.
- Head room column concrete work is completed.
- 1st floor block work is in progress.(70% completed).
- 1st floor block work is completed.
- 2nd floor block work is in progress.(70% completed).
- 3rd floor block work is in progress.
- Head room roof barbending work is in progress.
- 1st floor electrical wall chasing work is in progress.
- 2nd floor block work is completed.
- 3rd floor block work is in progress.(50% completed)
- Head room roof barbending work is in progress.
- 1st floor electrical wall chasing work is in progress.
- 2nd floor block work is completed.
- 3rd floor block work is in progress.(70% completed)
- Head room roof concrete work is completed.