Master Layout Plan
×
Approvals
Planning Permit No:
PPA/WDCN13/07259/2024
Date of Permit:
2024-08-17
Building Permission No:
BA/WDCN13/05820/2024
Date of Permit:
2024-08-17
Project Update Images
-
-
-
-
- Lift erection work is completed.
- Compound wall plastering work is in progress.(70% completed).
- All flats inner 1st coat painting work is completed.
- Wood work is in progress.(4 Flats progress)
- Outer chamber work is in progress.(90% completed)
- Duct covering work is in progress.
- Metro & drainage connection obtained.
- Lift erection work is completed.
- Compound wall plastering work is completed.
- All flats inner 1st coat painting work is completed.
- Wood work is in progress.(4 Flats progress)
- Outer chamber work is completed.
- Metro & drainage connection obtained.
- Outer painting work is in progress.(1st coat completed)
- GSB filling work is in progress.
- All flats inner 1st coat painting work is completed.
- Wood work is in progress.(4 Flats progress)
- Outer painting work is in progress.(1st coat completed,2nd coat progress)
- GSB filling work is completed.
- Outer chamber work is completed.
- Metro & drainage connection obtained.
- All flats inner 1st coat painting work is completed.
- Wood work is in progress.(4 Flats progress)
- Outer painting work is in progress.(1st coat completed,2nd coat progress)