Master Layout Plan
×
Approvals
Planning Permit No:
PPA/WDCN13/07259/2024
Date of Permit:
2024-08-17
Building Permission No:
BA/WDCN13/05820/2024
Date of Permit:
2024-08-17
Project Update Images
-
-
-
-
- External plastering work is in progress. (90% completed)
- 1st & 2nd floor toilet wall tile laying work is completed.
- 3rd floor main flooring work is completed.
- Terrace weathering course work is in progress(80% completed)
- Lobby flooring work is in progress.(80% completed)
- External plastering work is in progress. (90% completed)
- 1st floor general flooring work is in progress.
- Terrace weathering course work is in progress(80% completed)
- Lobby flooring work is in progress.(80% completed)
- External plastering work is completed.
- Stilt floor plastering work is in progress.
- Inner putty work is in progress.
- Lobby flooring work is in progress.(90% completed)
- General flooring work is in progress.(2nd &3nd floor completed,1ST floor progress)
- External primer work is in progress.
- Stilt floor plastering work is completed.
- Inner putty work in all floors is completed.
- Lobby flooring work is in progress.(90% completed)
- General flooring work is completed.
- Stilt floor common toilet plastering work is completed.